Contract procedure flow

Contract Procedures (for low voltage (less than 50kW))

If you have installed or modified renewable energy Power generation equipment and wish to purchase the renewable energy electricity generated by that equipment, you will need to apply to our company. The main steps required to start purchasing are as follows:

1. Application for Benefit Contract

申込代行者さま{icon"icon_arr04_right.svg"}九州電力

{icon"icon_arr04_down.svg"}

<Procedures for application agents and customers>

Business plan approval procedure

申込代行者さま・お客さま{icon"icon_arr04_lr.svg"}

{icon"icon_arr04_down.svg"}

2.Technology Review

Kyushu Electric Power Transmission and Distribution

{icon"icon_arr04_down.svg"}

3. Information on grid interconnection contracts

九州電力送配電{icon"icon_arr04_right.svg"}九州電力{icon"icon_arr04_right.svg"}申込代行者さま{icon"icon_arr04_right.svg"}お客さま

It will take approximately one month from the time you apply for the benefit contract until this notification is sent.

{icon"icon_arr04_down.svg"}

4. Installation of measuring instruments, etc.

Kyushu Electric Power Transmission and Distribution

{icon"icon_arr04_down.svg"}

5. Information on Electricity Supply Contract

九州電力{icon"icon_arr04_right.svg"}申込代行者さま(お客さま)

{icon"icon_arr04_down.svg"}

6. Start receiving benefits

九州電力{icon"icon_arr04_right.svg"}お客さま

{icon"icon_arr04_down.svg"}

7. Notification of power generation amount and payment

九州電力{icon"icon_arr04_right.svg"}お客さま

  • Each month, Kyushu Electric Power Transmission and Distribution will read Kyushu Electric Power Transmission and Distribution meter on Meter reading date set by the company, and will notify you of the amount of electricity we will purchase, the price, etc. on a "Purchased power amount Confirmation Sheet."
  • The fee will be transferred to the account you specify in advance.

Contract Procedures (High Voltage/Extra High Voltage)

If you have installed or modified renewable energy Power generation equipment and wish to purchase the renewable energy electricity generated by that equipment, you will need to apply to our company. The main steps required to start purchasing are as follows:

1. Advance consultation (optional)

申込代行者さま・お客さま{icon"icon_arr04_right.svg"}九州電力送配電

2. Connection Consideration Application

申込代行者さま{icon"icon_arr04_right.svg"}九州電力{icon"icon_arr04_right.svg"}九州電力送配電

It takes about one month from pre-consultation to application.

{icon"icon_arr04_down.svg"}

3. Answer to the connection consideration results

九州電力送配電{icon"icon_arr04_right.svg"}九州電力{icon"icon_arr04_right.svg"}申込代行者さま

We will respond within 2 to 3 months from the date of your connection application.

{icon"icon_arr04_down.svg"}

4. Connection contract application

申込代行者さま{icon"icon_arr04_right.svg"}九州電力{icon"icon_arr04_right.svg"}九州電力送配電

{icon"icon_arr04_down.svg"}

<Procedures for application agents and customers>

Business plan approval procedure

申込代行者さま・お客さま{icon"icon_arr04_lr.svg"}

{icon"icon_arr04_down.svg"}

5.Consent to interconnection, invoicing and payment of construction cost contributions

九州電力送配電{icon"icon_arr04_right.svg"}九州電力{icon"icon_arr04_right.svg"}申込代行者さま

{icon"icon_arr04_down.svg"}

6.Detailed Design

Kyushu Electric Power Transmission and Distribution

{icon"icon_arr04_down.svg"}

7. Contract Procedures

お客さま{icon"icon_arr04_right.svg"}九州電力

{icon"icon_arr04_down.svg"}

8. Start of Benefit Receipt

お客さま{icon"icon_arr04_lr.svg"}九州電力

{icon"icon_arr04_down.svg"}

9. Notification of power generation amount and payment

お客さま{icon"icon_arr04_lr.svg"}九州電力

Contract outline, application form, etc.

Contract details

Contract details, etc.

The terms of the contract for grid connection and electricity receipt when a power generation company supplies electricity generated by renewable energy Power generation equipment to our company and our company receives that electricity.

Application form

FIT (low pressure)

Please use this form when applying for FIT-certified renewable Power generation equipment with an output of less than 50kW.

FIT (high pressure)

Please use this form when applying for FIT-certified renewable Power generation equipment with an output of 50 kW or more.

Non-FIT (low pressure)

Please use this form when applying for non-FIT facilities (not scheduled to obtain FIT certification) with renewable energy Power generation equipment output of less than 50kW.

Non-FIT (high pressure)

Please use this form when applying for non-FIT facilities (not scheduled to obtain FIT certification) with renewable energy Power generation equipment output of 50 kW or more.

Battery interconnection

Please use this form if you are installing renewable energy Power generation equipment and a storage battery together.

Interconnection of Power generation equipment with reverse power flow of less than 50kW

Please use this form when applying for grid connection for Power generation equipment with a reverse power flow of less than 50kW to our company.