Characteristics of Temporary Lighting Plan /electricity
Rate Plan is for customers who mainly use electricity or power for construction projects lasting less than one year.
Eligible Customers
[Temporary Lighting Plan A]
Customers with a total capacity of 3kVA or less
[Temporary Lighting Plan B]
Customers with Contract ampere of 40A or more and 60A or less
[Temporary Lighting Plan C]
Customers with Contracted Electricity Capacity of 6kVA or more and less than 50kVA
[Temporary Power Plan]
(Fixed-rate supply) Customers with contracted power of 5kW or less
(Metered supply) Customers with contracted power exceeding 5kW and less than 50kW
Unit price
Temporary Lighting Plan A, B, C
(circle)
Classification
unit
Unit price
Temporary Lighting Plan A
Up to 50VA per day
1contract
7.40
Over 50VA up to 100VA per day
1contract
14.78
Over 100VA up to 500VA per 100VA per day
1contract
14.78
Over 500VA up to 1kVA per day
1contract
147.87
Over 1kVA up to 3kVA per 1kVA per day
1contract
147.87
Temporary Lighting Plan B
Base charge
10A
351.16
Power usage charge
1kWh
28.68
Temporary Lighting Plan C
Base charge
1kVA
351.16
Power usage charge
1kWh
28.68
- The unit price includes the equivalent of consumption tax, etc.
- For Temporary Lighting Plan B and C, Base charge will be half the amount if usage is 0 kWh.
Temporary Power Plan
(circle)
Classification
unit
Unit price
Fixed-price supply
1kW/day
205.81
Pay-per-use supply
Base charge
1kW
20% increase in applicable Low- Voltage Power charges
Power usage charge
summer
1kWh
20.88
Other seasons
1kWh
18.85
- The unit price includes the equivalent of consumption tax, etc.
- "Summer" refers to the period from July 1 to September 30. "Other seasons" refers to periods other than "summer."