Temperatures measured at the bottom of the Unit 2 Reactor Pressure Vessel at Fukushima Daiichi Nuclear Power Station

Here are the measurement results of temperatures at the bottom of the Unit 2 Reactor Pressure Vessel at Fukushima Daiichi Nuclear Power Station.

Monitoring points

Monitoring points

Temperature

Temperature
  • (注記)

    Here are the measurement points for each temperature.

  • (注記)

    For reference: The following is the “Limiting Conditions of Operations” designated in the implementation plan for temperatures
    at the bottom of the Reactor Pressure Vessel:
    ・Temperature at the bottom of the Reactor Pressure Vessel: Within 80°C

Announcement

  • Data may change or be missing due to equipment failure or regular inspections.
  • Temperature may change due to change of water injection flow rate to the reactor.
  • Instrument equipment is removed, installed or inspected for regular inspections at Unit 1 - 4.
    During the work period, the indicated value will fluctuate or be absent, but the equipment will return to a measureable state at a defined time.
  1. HOME
  2. Our Responsibilities to Fukushima
  3. Fukushima Daiichi decommissioning project
  4. Data
  5. Plant-related Parameters
  6. Temperatures measured at the bottom of the Unit 2 Reactor Pressure Vessel at Fukushima Daiichi Nuclear Power Station

Tokyo Electric Power Company Holdings

© Tokyo Electric Power Company Holdings, Inc.

AltStyle によって変換されたページ (->オリジナル) /