Uzbekistan : Central Asia Regional Economic Cooperation Road Corridor 2 Resilience and Modernization Project
Sovereign Project | 55244-002
The project road section is part of the A380 network between Bukhara and Nukus. The project will modernize a bypass section of the 4-lane dual carriageway of the A380 (581-673km) of about 92 km from Turtkul towards Nukus. The project will also develop the institutional capacity of the Committee for Roads under the Ministry of Transport, strengthen the traffic management and vehicle overloading control, improve the quality control of road works, and increase road safety. The project will also enhance climate change resilience measures by designing the road elevations, alignments and structures that are less susceptible to flooding, heavy snowfall, and landslides and that incorporates the adverse risks of climate conditions.
Latest Project Documents
Project Details
-
Project Officer
Kailasam, Ganesh
Sectors Group
Request for information -
Country/Economy
Uzbekistan -
Sector
- Transport
- Project Name
- Central Asia Regional Economic Cooperation Road Corridor 2 Resilience and Modernization Project
- Project Number
- 55244-002
- Country / Economy
- Uzbekistan
- Project Status
- Proposed
- Project Type / Modality of Assistance
- Loan
- Source of Funding / Amount
Loan: Central Asia Regional Economic Cooperation Road Corridor 2 Resilience and Modernization Project Source Amount Ordinary capital resources US$ 255.00 million - Operational Priorities
- OP1: Addressing remaining poverty and reducing inequalities
- OP3: Tackling climate change, building climate and disaster resilience, and enhancing environmental sustainability
- OP5: Promoting rural development and food security
- OP7: Fostering regional cooperation and integration
- Sector / Subsector
Transport / Road transport (non-urban)
- Gender
- Effective gender mainstreaming
- Description
- The project road section is part of the A380 network between Bukhara and Nukus. The project will modernize a bypass section of the 4-lane dual carriageway of the A380 (581-673km) of about 92 km from Turtkul towards Nukus. The project will also develop the institutional capacity of the Committee for Roads under the Ministry of Transport, strengthen the traffic management and vehicle overloading control, improve the quality control of road works, and increase road safety. The project will also enhance climate change resilience measures by designing the road elevations, alignments and structures that are less susceptible to flooding, heavy snowfall, and landslides and that incorporates the adverse risks of climate conditions.
- Project Rationale and Linkage to Country/Regional Strategy
- Being surrounded by Kazakhstan to the north, Kyrgyz Republic to the northeast, Afghanistan to the south, Turkmenistan to the southwest, and Tajikistan to the southeast, Uzbekistan is a double landlocked country, which requires crossing at least two countries to reach the nearest seaport access. With a population of 36 million people, the road modernization will substantially improve the land-based surface transport networks, specifically for Central Asia Regional Economic Cooperation Corridor. Improving the connections of these road linkages will support the efficient movements of trade to neighboring seaports.
- Impact
Regional trade and economic connectivity on the Central Asia Regional Economic Cooperation Corridor 2 is enhanced, particularly between Uzbekistan and Kazakhstan.
- Outcome
Road transport connectivity, efficiency, and safety in Western Uzbekistan improved.
- Outputs
Resilient and modernized CAREC Road Corridor 2.
Capacity support for institutional development and strengthening provided to the Committee of Roads.
- Geographical Location
- Nukus
Safeguard Categories
- Environment
- A
- Involuntary Resettlement
- A
- Indigenous Peoples
- C
Summary of Environmental and Social Aspects
- Environmental Aspects
- Due diligence work is ongoing. Project is expected to be categorized as A because significant environmental impact is expected.
- Involuntary Resettlement
- Due diligence work is ongoing. Project is expected to be categorized as A because significant involuntary resettlement impact is expected.
- Indigenous Peoples
- Due diligence work is ongoing. Project is expected to be categorized as C.
Stakeholder Communication, Participation, and Consultation
- During Project Design
- Stakeholders consultations will be conducted especially in preparing and completing the required safeguards documents.
- During Project Implementation
- Stakeholders consultations will be conducted whenever necessary.
Business Opportunities
- Consulting Services
- Consulting firms will be selected and engaged using the quality- and cost-based selection (QCBS) method, where applicable. Recruitment for construction supervision consultant will use 90:10 quality-cost ratio. The external financial auditor which will be selected using the least-cost selection (LCS) method. The terms of reference for all consulting services will be discussed in detailed in the PAM.
- Procurement
- The procurement of the works and the selection of consultant services will follow the new procurement framework as set out in ADB's Procurement Policy for the procurement of goods, works, consulting services and non-consulting services (2017, as amended from time to time) and the Procurement Regulations for ADB Borrowers (2017, as amended from time to time). Open competitive bidding (OCB) with international advertising will be used for procurement of the road works package with estimated value of 219ドル.0 million; and procurement of two contracts for the design, supply and installation of WIM and ITS, with total estimated value of 13ドル.3 million. OCB with national advertising will be used for one contract to renovate the community center with estimated value of 1ドル.0 million. The latest version of ADB's standard bidding documents and request for proposals will be used.
Contact
- Responsible ADB Officer
- Kailasam, Ganesh
- Responsible ADB Department
- Sectors Group
- Responsible ADB Division
- Transport Sector Office (SG-TRA)
- Executing Agencies
-
Committee for Roads
Timetable
- Concept Clearance
- 13 Oct 2023
- Fact Finding
- 20 May 2024 to 31 May 2024
- MRM
- -
- Approval
- -
- Last Review Mission
- -
- Last PDS Update
- 21 Oct 2023
Funding
Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.
The Access to Information Policy (AIP) recognizes that transparency and accountability are essential to development effectiveness. It establishes the disclosure requirements for documents and information ADB produces or requires to be produced.
The Accountability Mechanism provides a forum where people adversely affected by ADB-assisted projects can voice and seek solutions to their problems and report alleged noncompliance of ADB's operational policies and procedures.
In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
Title | Document Type | Document Date |
---|---|---|
Central Asia Regional Economic Cooperation Corridor 2 Resilience and Modernization Project: Initial Poverty and Social Analysis | Initial Poverty and Social Analysis | Oct 2023 |
Safeguard Documents See also: Safeguards
Safeguard documents provided at the time of project/facility approval may also be found in the list of linked documents provided with the Report and Recommendation of the President.
Title | Document Type | Document Date |
---|---|---|
Central Asia Regional Economic Cooperation Road Corridor 2 Resilience and Modernization Project: A380 Road Environmental Impact Assessment | Environmental Impact Assessments | Jun 2024 |
Central Asia Regional Economic Cooperation Road Corridor 2 Resilience and Modernization Project: Land Acquisition and Resettlement Plan | Resettlement Plans | May 2024 |
Evaluation Documents See also: Independent Evaluation
None currently available.
Related Publications
None currently available.
The Access to Information Policy (AIP) establishes the disclosure requirements for documents and information ADB produces or requires to be produced in its operations to facilitate stakeholder participation in ADB's decision-making. For more information, refer to the Safeguard Policy Statement, Operations Manual F1, and Operations Manual L3.
Requests for information may also be directed to the InfoUnit.
Tenders
Contracts Awarded
Procurement Plan
None currently available.