Fukushima Daiichi Timeline after March 11,2011

  • English
  • Search Results ()
    TEPCO

    © Tokyo Electric Power Company Holdings, Inc.

    Search

    Abbreviations

    ALPS
    : Advanced liquid processing system
    FHM
    : Fuel handling machine
    PCV
    : Primary contaiment vessel
    R/B
    : Reactor building
    RO
    : Reverse osmosis
    RW/B
    : Radioactive waste disposal building
    SFP
    : Spent fuel pool

    2011

    All reactors in cold shutdown

    2012

    Start making full-scale measures against contaminated water

    2013

    Struggled in efforts to deal with issues

    2014

    Completion of fuel removal from Unit 4 spent fuel pool

    2015

    Completion of contaminated water treatment

    2016

    Start of full-scale investigation for fuel debris removal

    2017

    Fuel debris removal methods for each Unit determined

    2018

    Prepare for fuel removal from Units 3 spent fuel pool

    2019

    The method employed to retrieve fuel debris for the first unit will be confirmed

    2020

    Dismantling of the Unit 1/2exhaust stack in cooperation with a local company

    2021

    Completion of fuel removal from Unit3 spent fuel pool

    2022

    In Preparation for Fuel Debris Retrieval from Unit 2

    2023

    Commencement of the discharge of ALPS treated water into the sea

    2024

    Fuel debris trial retrieval completed for the first time after the accident

    2025

    Toward installing the large cover at Unit 1