Information of Kashiwazaki-Kariwa Nuclear Power Station (The 8th news)
- Status of main inspection and restoration work (1) -
At present, the Kashiwazaki Kariwa Nuclear Power Station is systematically and steadily undertaking detailed inspections and restoration work on its equipment and facilities, with the results of the inspections to be released as they become available.JANTI will summarize the findings and release them in coming months. This Report #8 introduces the current status of main inspection and restoration work.
Report #6 provided the “update on the overall situation through to August 10”.Our next report will give another update on subsequent progress made.
Overall inspection schedule (planned):Excerpt from TEPCO press release dated September 6
Inspection results
In-core inspection (Phase 1) was conducted on Unit 1 from August 21 to 23, to find no damage, deformation or dislodgment of parts.
In-core inspection (Phase 2:Inspection of the mid reactor --- the reactor core) on Unit 1 is scheduled for September 14 to October 1.
<Phase 1 (Inspection of the upper reactor)>
The internals of a reactor are visually checked from above with an underwater camera, before the implementation of further inspection on the area extending from the reactor pressure vessel flange to the upper grid plate, with the aim of checking the internal status of the reactor.
<Phase 2 (Inspection of the mid reactor --- the reactor core)>
An underwater camera is used to visually check the area extending from the upper grid plate to the core support plate, as well as the outer circumference of the core shroud (annulus).The dryer and separator, removed from the core, are also examined.
<Phase 3 (Inspection of the bottom of the reactor)>
Inspection is carried out on the area extending from the core support plate to the bottom of the reactor, after removing control rods, fuel supports and other items that could interfere with the inspection.
Related information on in-core inspection on Unit 1 (posted on the TEPCO website)
Japan Nuclear Technology Institute
Rev.0
September 19, 2007