How often does a US interconnection request actually get built?

Everyone quotes the queue headline — "466 GW in ERCOT", "699 GW in MISO" — as if it were a pipeline. Most of it never gets built. This measures how much.

Answer: 17.2%–21.4% of resolved requests were built. The naive figure is 14.2%, and it is wrong for a specific reason given below.

The number that matters for the AI-power trade: requests of 1,000 MW or more were built 5.3% of the time (95% CI 2.8–9.8, n=169).

What the data is

Four ISOs publish their full interconnection queue with outcomes, no credentials required:

ISO requests built withdrawn still active
MISO 3,828 562 2,143 1,123
NYISO 3,139 151 2,802 186
CAISO 2,278 251 1,762 265
ISONE 1,751 362 1,326 63
total 10,996 1,326 8,033 1,637

Three do not:

  • PJM — requires a free PJM_API_KEY. Worth getting: PJM is the largest datacenter market that publishes a queue at all. Register at apiportal.pjm.com, verify the email, then copy the Primary key from your profile's subscriptions into .env.
  • ERCOT — 403s all scripted access. Publishes large-load only in aggregate.
  • SPP — ops portal times out from here; may be transient.

Fetching is done through gridstatus, which normalises all seven ISOs onto one schema. There was no reason to write another scraper.

Why the naive number is wrong

built / (built + withdrawn) over everything gives 14.2%. That is too low, because a request filed in 2024 has not had time to be built and is counted as though it had already failed. Censoring is being read as attrition.

So every rate here is computed per queue-year cohort, and a cohort is only quoted once ≥90% of it has reached a terminal state. On that basis the rate is 21.4% (n=5,436).

That number is biased the other way. 1,354 resolved records have no queue date and fall out of every cohort — and they are 1,351 withdrawals to 3 builds (mostly pre-2000 NYISO rows). If all of them belonged to quotable cohorts the rate would be 17.2%.

Hence the range. Neither end is quoted alone.

What actually predicts attrition

Restricted to resolved requests in quotable cohorts (n=5,436). Wilson 95% intervals, because several segments sit close to zero where the normal approximation misbehaves.

By size — the strongest and cleanest effect:

capacity n build rate 95% CI
<20 MW 1,024 28.8% 26.1–31.7
20–100 MW 1,639 19.0% 17.2–21.0
100–300 MW 1,654 23.9% 21.9–26.0
300–1,000 MW 680 12.6% 10.4–15.4
≥1,000 MW 169 5.3% 2.8–9.8

Monotone above 100 MW, and the gigawatt bucket is an order of magnitude below the small one. This is the commercially relevant cut: the AI datacenter power story is entirely about gigawatt-scale interconnection, which is the size class that historically almost never completes.

By fuel, after normalising the ISOs' vocabularies:

fuel n build rate 95% CI
gas 625 33.1% 29.5–36.9
solar 1,885 23.2% 21.3–25.1
wind 861 19.5% 17.0–22.3
storage 724 9.5% 7.6–11.9

Two bugs caught while building this

1. Mixed date formats silently destroyed 7,400 of 9,640 dates. The four ISOs write queue dates four ways (2003年11月18日 08:00:00, 1/14/2025, 2025年10月08日T00:37:52+00:00, 2008年01月30日). pd.to_datetime infers a single format from the first non-null value and coerces everything that disagrees to NaT. Parsed as one column, 84% of dates vanished — and the loss is indistinguishable from ordinary missingness, so nothing downstream complained. Caught only because baserate.py cross-tabulates date-missingness against outcome before using cohorts. Dates are now parsed per ISO, with an assertion that ≥98% of present values survive.

2. Unnormalised fuel labels invented a finding. The raw segment table reported Solar 32.1% next to Photovoltaic 13.0% and Wind 19.1% next to Wnd 26.9%. Same technologies, different ISO vocabularies — the gap was measuring ISO composition. fuel.py maps them onto one set and prints the fuel×ばつISO crosstab so the remaining confound stays visible.

The portfolio question: do outcomes move together?

src/frailty.py. A probability per project answers "will this one be built". It does not answer "how much will my forty projects deliver", and the gap between those two questions is entirely about whether outcomes are independent. They are not.

Stage 1 — is there anything to model? Given honest out-of-sample probabilities, group build counts are compared with what independent Bernoulli draws would produce. The comparison is against a permutation null — same probabilities, same group sizes, group membership shuffled within queue year — because the model is miscalibrated and miscalibration inflates raw dispersion on its own. A chi-square table would have found "correlation" that was really the model saying 65 and meaning 49.

shared by groups dispersion permuted null inflation
fuel 13 13.23 3.24 4.09x
state 27 5.64 2.15 2.62x
ISO study cycle 59 7.41 3.93 1.88x
county 132 2.14 1.19 1.80x
ISO 4 15.41 8.77 1.76x
transmission owner 22 4.32 2.51 1.72x

All p < 0.00025, the floor at 4,000 permutations. Technology is the strongest shared shock, ahead of geography — tariffs, cell prices and turbine lead times hit every project of a type at once.

Stage 2 — how big is the shock? A random-intercept logit fitted by marginal maximum likelihood, integrating the group effect out with Gauss-Hermite quadrature. The study cycle carries tau = 1.06 on the log-odds scale, an ICC of 25.5%. Levels are fitted one at a time and therefore overlap, so the structure is chosen by test rather than by taking the largest tau.

Stage 3 — does it actually predict better? Books of 40 are drawn from held-out data and scored against each structure's predicted distribution. The target for an 80% interval is 80%:

book independent cycle+fuel+county
random 78.7% 89.0%
all one state 74.5% 88.1%
all one fuel 62.6% 81.5%

Independence is tolerable for a diversified book and dangerous for a concentrated one — which is the realistic case for a developer or a lender. On a single-fuel book its 80% interval contains the truth 62.6% of the time.

On the live book of 1,637 active requests, the frailty distribution is 4.3x wider than independence implies and its 1-in-10 bad case is 21.6 GW worse.

Read the shape, not the level

Two measured reasons the central estimate deserves less trust than the spread:

  1. Count calibration is not capacity calibration. Probabilities calibrated so that each project is right overstate delivered capacity by +20.8% out-of-sample, because gigawatts sit in large projects and large projects fail more inside every size band. Re-fitting the calibration weighted by megawatts cuts the bias to +6.1% for 0.0007 of Brier. Adding a size band as a feature does not fix it — the bias is within bands, not between them.
  2. The live book is 68% MISO by capacity against 19% in training. The headline therefore rests largely on one operator's record. 18% of the book's capacity sits in (iso, fuel) cells with fewer than 40 resolved historical requests; support() prints them.

The dispersion result is a ratio and survives both. The central estimate does not, and is quoted with that attached.

Known limitations

  • Fuel and ISO are not fully independent. Solar, wind, gas and storage appear in all four ISOs, so the fuel table is not purely an ISO artifact, but it is not a controlled comparison either. The crosstab is printed; read it before quoting a fuel number.
  • CAISO's public queue report stops at 2023年03月02日. Recent CAISO activity is absent.
  • MISO's queue only goes back to 2015 (its queue was reset).
  • Status reflects an ISO's bookkeeping, not physical reality. "Completed" means the interconnection agreement completed, not that electrons flowed.
  • Nothing here is a forecast. These are historical base rates. No model has been fit and no out-of-sample claim is made.

The archive — why this is the only part that compounds

The ISOs publish current state only. Status, Capacity (MW), Proposed Completion Date, inService and studyPhase are overwritten in place on every refresh. When a 400 MW request is revised to 250, or a 2027 in-service date slips to 2029, the previous value is not archived anywhere — not by the ISO, not by gridstatus, not by the aggregators.

So the revision history cannot be bought, back-scraped, or reconstructed. It can only be accumulated from the first day someone starts. Every day without a snapshot is a day of history that is gone permanently.

./venv/bin/python src/snapshot.py # append-only, content-addressed
./venv/bin/python src/diff.py MISO # change events between the last two
./venv/bin/python src/health.py # days since each ISO last captured

This runs automatically. scripts/daily_snapshot.sh is driven by a launchd agent (~/Library/LaunchAgents/com.savabs.queue-snapshot.plist) at 09:15 daily and again at login — launchd runs a missed job once on the next wake rather than skipping the day, and duplicate runs are free because snapshots are content-addressed. The job commits data/snapshots only, so it can never sweep up unfinished source edits, and it runs src/health.py every time because a snapshot job that dies quietly is the one failure that cannot be repaired later.

Credentials

Copy .env.example to .env and fill it in. Do not export keys in ~/.zshrc — launchd starts jobs with a nearly empty environment and reads no shell profile, so a key set that way works when you test it by hand and is absent every night in the scheduled run, failing with a network-shaped error that looks exactly like the source being down. src/env.py loads .env on the Python side and the wrapper sources it on the shell side, so manual and automated runs behave identically.

./venv/bin/python src/check_keys.py # verify a key actually works
launchctl list | grep queue-snapshot # is it loaded
tail -40 data/snapshots/run.log # what it did last
launchctl unload -w ~/Library/LaunchAgents/com.savabs.queue-snapshot.plist # stop it

Snapshots are hashed on content, so an unchanged refresh costs nothing and still leaves a dated entry in data/snapshots/index.jsonl.

Queue ID is not a primary key and diffing on it corrupts the history silently. ISONE reuses position 73 across eight different plants; NYISO leaves it null on 1,350 historical rows and reuses 0031 for Astoria Phase 1 (Completed) and Phase 2 (Withdrawn). Identity is therefore a composite — Queue ID + Project Name + County + Interconnection Location + Queue Date — widened only until unique, and rows that still cannot be keyed are reported and excluded from change tracking rather than guessed at (MISO 2, ISONE 8, NYISO 1,350).

No watched field may appear in the identity key, or a revision would read as a departure plus an arrival instead of a change. src/diff.py asserts this.

Running it

./venv/bin/python src/fetch.py # pull the queues (network)
./venv/bin/python src/build.py # label outcomes -> data/queue_attrition.csv
./venv/bin/python src/baserate.py # cohort-corrected base rates
./venv/bin/python src/segments.py # by ISO, fuel, size, transmission owner

src/build.py keeps Status, Withdrawn Date, Actual Completion Date and Withdrawal Comment out of the feature set — each is only knowable after the outcome it would be used to predict — and asserts it.

External check

LBNL's Queued Up reports that 75% of capacity requesting interconnection 2000–2020 had withdrawn by end-2025. This dataset gives 88.8% of MW withdrawn across four ISOs on an uncorrected basis. The two are not directly comparable (different ISO coverage, different windows, capacity vs count, and the 88.8% carries the censoring bias described above) but they agree that the large majority of queued capacity never gets built.

About

Calibrated probabilities on whether US interconnection requests ever get built. Base rates, an append-only prediction ledger, a daily snapshot archive, and a shared-frailty portfolio model.

Topics

Resources

Stars

0 stars

Watchers

0 watching

Forks

Releases

Packages

Contributors

Languages

AltStyle によって変換されたページ (->オリジナル) /