Theme1: Making changes in the output specification
The topics to discuss by the moderator is:
1. How each country's approach on the policy and process might differs from others.
2. Procedure for making changes to the output specification
3. Determining the price for the modification
4. Method of payment
Executive Manager,
Partnerships Victoria
Commercial Division
Department of Treasury and Finance
PPP contracts in Australia typically provide that government may
initiate modifications to the facility and the service specifications at
any time during the contract term. The cost of government-initiated
modifications is borne by government, although it may be financed by the
contractor and recovered through the service payments over the remaining
life of the contract.
The following describes the Standard
Commercial Principles that we apply to modifications (including changes to
the output specification) in our Partnerships Victoria projects, and some
of our experiences to date. Please consider how our approach might differ
from your own, and use this as a starting point for discussion and
comments on the policy and process issues associated with making changes
to the output specification.
Under our principles, the contractual
modifications process does not apply to:
1. Minor changes to the
facility that do not exceed an agreed threshold,
2. Any refurbishment
and maintenance works required during the operational phase, and
3. Any other changes or alterations required to ensure the facility is fit for
its intended purpose (the contractor is obliged to maintain a "fit for
intended purpose" facility, and bears all costs associated with this)
Any modifications proposed by the private party are implemented at
the private party's own cost following approval by the State.
Modifications due to a change in law are dealt with under the
change in law provisions in the contract.
PROCEDURE FOR MAKING CHANGES TO THE OUTPUT SPECIFICATION
In Victoria there
are no specific restrictions on negotiating with the existing contractor
with regard to modifications, but the State would consider on a
case-by-case basis whether any modification should be separately tendered
in order to obtain the best value for money outcome. In almost all cases,
interface risk is best managed by having the existing Contractor implement
the modification. This is particularly the case where the focus of the
modification is on changes to the output specification rather than changes
to the physical facility.
It is important to note that major
changes early in the project life could lead to legal challenges by losing
bidders on the basis that they could have won the bid had the modified
project been put to the market in the first place.
Government may at any time request a modification to the facility by serving a notice on
the private party.
Within a defined period after government's
request, the private party must give government its proposal for carrying
out the proposed modification, including details of any effect on the
facility and delivery of the contracted services, necessary capital
expenditure, any impact on recurrent costs (on a fully transparent basis)
and, where necessary, how the private party will fund the costs.
As a practical matter, it is generally preferable for the State to
discuss the proposed change informally with the Contractor prior to
initiating the formal contractual change process. This ensures that the
formal change request reflects a joint understanding of the potential
risks and constraints of the change.
Where a project is undertaken
in a new sector, for which there is little experience in developing output
specifications, the parties may find after a year or two of operations
that a small proportion of the performance requirements in the contract
are not as easily measured as expected, or do not appropriately
incentivise performance that best meets government's needs. In these
circumstances, the parties may seek to make changes in the specifications
that produce a "win-win" outcome by providing greater clarity and more
appropriate incentives.
DETERMINING THE PRICE FOR THE MODIFICATION
Our contracts include detailed modification
compensation principles to ensure that the State receives value for money
when it requests modifications.
The State will pay reasonable
costs arising as a direct result of carrying out the modification works,
including an allowance for profit, and incremental changes in overhead,
management and administration costs at rates agreed in the contract (which
may depend upon the total value of the modification).
An allowance may also be made for delay costs or prolongation costs arising directly
from the modifications.
The private party must provide evidence
that it has used reasonable endeavours to ensure that sub-contractors
minimise costs and maximise any reduction in costs.
Where the parties cannot agree upon sub-contractor costs for a modification, the
contract to implement the modification works may be awarded by competitive
tender, and the private party must appoint the tenderer whom the parties
agree offers the best value for money.
METHOD OF PAYMENT
Any payment made by the State to the private party for
the modification will be made on a whole-of-life basis (that is, it will
take into account both the positive and negative effect of the
modification on recurrent expenditure, as well as the capital
cost).
Significant modifications outside the scope of the original
project that require extra funding have to go through the normal budgetary
allocation process.
There are three mechanisms for compensating the Contractor for modification works:
1. up-front reimbursement
of costs of capital works, or
2. by increasing the amounts of the service payments over the remaining contract term, or
3. by extending
the contract term.
The mechanism used is determined by negotiation
between the State and the Contractor. From the State's perspective, a
range of issues need to be taken into account when negotiating the form of
payment. If the State makes an up-front payment, this will not be subject
to abatement for sub-standard performance in future. Conversely, if the
modification will be paid for by increasing the amounts of the service
payments over the remaining contract term, the State must consider to
total cost, which will include the contractor's financing costs, in
determining whether this option offers value for money.
Thank you to my colleague Tara Spivakovsky for her input to this discussion.
Kind regards,
[2]
Author: Nicholas Jennett
Date: 2008年04月18日
Organization:
Structured Finance & Advisory - AGI/EU
European Investment Bank
Dear Richard and Tara
Thank you for this extremely
interesting contribution. I have a couple of questions that I would
like to pose - these mostly concern financing aspects.
You indicate that the SPV must make reasonable endeavours to minimise
sub contractor costs. What are its obligations in respect of
securing funding where the authority is not paying the capital up
front? Can it simply go to exsiting funders, or is there some form
of benchmarking, or even competitive element? Where an incumbent
funder is not chosen to fund the change, how will this work in
respect of, for example, new inter creditor arrangements?
Related to this, what powers to funders have to prevent a
change? In particular, if a change fundamentally altered the nature
of a project, this could undermine the strength of the credit from
the funders' perspective.
Finally, how are equity returns
potentially affected by a change? I assume that equity has the right
to prevent any change that would undermine returns, but are equity
returns capped out at the original base case as part of the
negotiation of the cost of the change?
Do you, or other participants, have examples of projects where these issues have been
worked through in practice?
Thank you
Nick
[3]
Author:Susan Tinker
Date: 2008年04月20日
Organization:
Assistant Vice-President,
Procurement Services
partnerships British Columbia
HI all.
I will be posting a response to Richard and Tara's
original post on Monday. I have an additional question though, which we
are currently struggling with. For hospital projects, do your output
specifications focus on performance during the operations period, and if
so, what kind of performance measures are you using. For example, are you
using efficiency measures for medical staff? If yes, I would like to learn
more about the kinds of measures you use.
Thanks,
[4]
Author: Richard Foster, Moderator
Date:2008年04月28日
Organization:
Executive Manager,
Partnerships Victoria
Commercial Division
Department of Treasury and Finance
Here are some thoughts on the comments from Nicholas Jennett
and Susan Tinker. Thanks again to my colleague Tara Spivakovsky for
her input.
A. The SPV's obligations in respect of securing
funding where the authority is not paying the capital up
front.
Whether modifications are paid for up-front, by an
extension of term of the contract or an increase in the service
payment over the life of the contract is a matter for negotiation
between the parties. Where the government initiates modifications,
the Contractor must put forward a proposal on how it intends to
achieve those modifications, including any necessary funding.
Government approval is required for the Contractor's proposal,
including the funding arrangements. The government can refuse to
approve the funding proposal - however if government does this it
must then be prepared to forgo the modifications or fund them
up-front itself.
Where government does not elect to make a
capital expenditure payment, the private party is required to use
all reasonable endeavours to obtain additional or alternative
funding to pay for any necessary capital works. New or additional
funding is generally subject to various restrictions considered
necessary by government under the circumstances, including:
- Where the new/additional funding is debt finance, any increase in
the service charge should not me more than the amount required to
amortise the loan amount (and interest) over the term of the loan; and
- Where the new/additional funding is in the form of
equity, the increase in the service charge is not to be greater than
the amount required to give the equity holders the prevailing market
rate of return on the additional funding.
B. Issues arising where new funders are brought in to fund the change
The contractor's obligation only extends to using "reasonable
endeavours" to obtain funding for the change. Therefore, if existing
funders are unwilling to fund modifications the Contractor must
approach third parties, and the Contractor and both the new and
existing funders will have to negotiate suitable inter-creditor
arrangements. (The new funders will also have to agree to enter into
a funder's direct agreement with government.) If, despite using all
reasonable endeavours, the Contractor cannot secure agreement of
both the new and existing funders, the contractor will not be
obliged to fund the change.
Should they chose not to fund the
change, the existing funders do not have rights to prevent the
change - the contractor will either obtain alternative funding, or
government will have to pay the capital cost up front. From a policy
perspective, it would not be acceptable to government (at least in
social infrastructure projects) to have a contract under which the
funders were entitled to veto a change.
C. Impact of changes on equity returns
During the bid phase for the project, the
contractor is required to bid fixed or maximum margins and other
on-costs that it may apply to the cost of modifications over the
life of the project.
As noted above, where new/additional
funding for a change is in the form of equity, the increase in the
service charge is not to be greater than the amount required to give
the equity holders the prevailing market rate of return on the
additional funding.
D. Do you, or other participants, have
examples of projects where these issues have been worked through in
practice?
We have had a number of relatively small changes
implemented on a number of projects. Some of these have been funded
by the contractor, and for others the capital cost has been paid up
front by government. However none of these changes have been large
enough to significantly alter the risk profile or funding needs of
the project.
E. Output specifications during the operations
period for hospital projects
For all our hospital projects,
all medical services are still provided by the government - only
facility management and ancillary services, such as cleaning, are
provided by the Contractor. A detailed list of KPIs with different
consequences and cure periods is implemented to ensure performance
and focus most attention on critical areas. For example, lack of
availability of critical function such as an operating theatre has
an immediate impact on the service payment whereas non-critical
breaches have longer periods for rectification and a lesser effect
if this deadline is not met. This is accomplished through a points
system where Quality Failure points are awarded for each breach and
its duration. Where fundamental breaches occur, such as the HelpDesk
not operating, they are categorised as Failure Events. We have not
included performance measures related to performance or efficiency
of the public sector hospital operator, as the contractor's ability
to influence these aspects is limited in comparison to the impact
that the operator will have. However, in some projects where
specific efficiency gains for government form part of a winning
bidder's proposal, it may be possible to include performance
measures related to the availability of these efficiency gains once
the project is operational.
[5]
Author: Hirohiko Machida
Date:2008年07月02日
Organization:
Director,
PFI promotion office
Cabinet office of Japan
1.How each country's approach on the policy and process might
differs from others.
We have no statute which regulates procedures
for change in output specifications in PFI projects (though there are a
few general rules applicable both to PFI and traditional procurements.)
Our guidance for PFI contracts, which was published in 2003, also does not
provide the process.
Thus, the change process differs by projects.
Now, we are preparing new guidance for it as a part of standardization of
Japanese PFI contracts. We plan to publish its exposure draft in
summer.
The essence of our current draft guidance for change procedure
is as follows:
(1) Both parties should realize the importance of
the flexibility. The government should not make de facto change or should
not leave the necessity of the change.
(2) On the other hand, initial
output specifications should be clear even if there is possibility that
they will be amended in near future. If they are unclear, in the cases of
changes, it becomes difficult for parties to objectively calculate the
amount of additional payment.
(3) The cost for government-initiated
change should be borne by the government. The price determination process
should be fair and transparent. The government should not impose
unreasonable burden on the contractor.
(4) As for small changes,
simplified procedure is necessary (discussed later).
(5) Where it is
expected that there will arise some gaps between output specifications and
reality, the PFI contract may provide bedding-in-period and/or periodic
review procedures.
2. Procedure for making changes to the output
specification/ Determining the price for the modification
Until now, in many PFI contracts in Japan, change procedures are not so clear.
It is said that, in some cases, governments forced contractors to make
changes in service specifications without payment because of lack of clear
procedures. Thus, for the purpose of fair risk allocation, we are
preparing principles for clear change procedures as a part of
standardization of PFI contracts. In our draft, we proposed change
procedures which are similar to those presented by Mr. Foster.
The price determination process depends on the size of the proposed change.
As for smaller changes, we are considering the catalogue method where
all-included price for each change is listed, and a kind of open-book
method where the price is calculated based on unit prices used for the bid
for PFI contract and margin. However, we have no experience to use such
methods in PFI projects, therefore we are not so confident whether these
measures are applicable to Japanese situation or not.
As for larger changes, we have considered the three methods: bench marking, market
testing, and independent expert appraisal, which are mentioned in
Standardisation of PFI Contracts version 4 in UK. However we understand
that it is very difficult to determine which method should be used as a
default method.
Though we realized issues to be discussed, we have not
reached conclusion.
If you have some tips for price determination,
we would appreciate it if you would put your comments.
3. Method of payment
At first we believed that the public sector should make
lump-sum payment in the case of capital expenditure. However some argued
that the requirement will prevent some local governments from making major
changes.
We have not reached conclusion on that point, and we
would appreciate it if you could post comments on (1) pros and cons of
reasonable endeavour approach, and (2) other approaches than reasonable
endeavour approach.