Bartleby Related Questions Icon

Related questions

Question
Use the following data to answer questions
BAC = 24,000ドル
BCWSc = $ 5,333
BCWPc = $ 6,400
ACWPc = $ 6,800
CV = 400ドル
SV = 1,067ドル
CPIa = 0.94
SPIa = 1.20

1: Perform the following analyses of the project based on the data given above.
a) Estimate at Completion (all three methods)
b) Estimate to complete
c) Variance at Completion
d) To-Complete Performance Index
e) Project Percent Analysis (planned, earned, and actual cost)
2: Interpret results to address the following two points.
a) Which method produces the best results?
b) In what circumstances is a particular method more appropriate for analysis?
Expert Solution
Check Mark
Knowledge Booster
Background pattern image
Recommended textbooks for you
Text book image
Engineering Fundamentals: An Introduction to Engi...
Civil Engineering
ISBN:9781305084766
Author:Saeed Moaveni
Publisher:Cengage Learning
Text book image
Fundamentals Of Construction Estimating
Civil Engineering
ISBN:9781337399395
Author:Pratt, David J.
Publisher:Cengage,
Text book image
Traffic and Highway Engineering
Civil Engineering
ISBN:9781305156241
Author:Garber, Nicholas J.
Publisher:Cengage Learning
Text book image
Residential Construction Academy: House Wiring (M...
Civil Engineering
ISBN:9781285852225
Author:Gregory W Fletcher
Publisher:Cengage Learning
Text book image
Sustainable Energy
Civil Engineering
ISBN:9781337551663
Author:DUNLAP, Richard A.
Publisher:Cengage,