Question
In the following MRP planning schedule for Item J, indicate the correct net requirements, planned-order receipts, and planned-order releases to meet the gross requirements. Lead time is one week.
Note: Leave the cells blank, whenever zero (0) is required.
| ITEM J | WEEK NUMBER | ||||
|---|---|---|---|---|---|
| 0 | 1 | 2 | 3 | 4 | 5 |
| Gross requirements | 73 | 55 | 74 | ||
| On-hand | 43 | ||||
| Net requirements | |||||
| Planned-order receipt | |||||
| Planned-order release |
Transcribed Image Text:Problem 9-10 (Algo)
In the following MRP planning schedule for Item J, indicate the correct net requirements, planned-order receipts, and
planned-order releases to meet the gross requirements. Lead time is one week.
Note: Leave the cells blank, whenever zero (0) is required.
ITEM J
Gross requirements
On-hand
Net requirements
Planned-order receipt
Planned-order release
WEEK NUMBER
0
1
2 3 4
73
5
55
74
43
Period
1
2
3
4
5
73
55
74
Item: J
OH: 43
LT: 1
SS: 0
Q: L4L
Gross requirements
Scheduled receipts
Projected available balance
Net requirements
Planned order receipts
Planned order releases
Expert Solution
Check MarkThis question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
bartleby
Step by stepSolved in 2 steps
Knowledge Booster
Background pattern image
Recommended textbooks for you
- Text book image
Text book image