Question

Help me with is please!!!

[画像:#2 Add Fixed Costs to Schedule Complete the forward pass, backwards pass, and float calculations on the AON diagram below, and enter it in Microsoft Project as a new project, using Monday, 1/6/2025 as the start date. Critical Path of both the Gantt chart and the AON should match. Mobilize 1 1,000ドル Activity Description ES Duration EF LS Float Costs LEGEND I Setup Scaffold 6 Remove Roof 1,700ドル 5,500ドル Shut Off Electric 4 300ドル Pay Dump Fees 4 600ドル Fill Dumpster 4 1,800ドル New Roofing 8,000ドル Trash to Landfill 3ドル.400 A Add columns "Fixed Cost", "Remaining Cost", and "Actual Cost to schedule B. Add Costs from the AON above to the "Fixed Cost" column C. Set the baseline D. Update the project to 100% complete through 1/20/2025 E. Print out to PDF a "Cash Flow" report with the following items completed: a Name added in the second box on the right b. Update the graph to show "Cost" as bars on primary axis, and "Cumulative Cost" as a line on secondary axis, and days as the primary unit of time. Final Clean 2 1,500ドル]
expand button
Transcribed Image Text:#2 Add Fixed Costs to Schedule Complete the forward pass, backwards pass, and float calculations on the AON diagram below, and enter it in Microsoft Project as a new project, using Monday, 1/6/2025 as the start date. Critical Path of both the Gantt chart and the AON should match. Mobilize 1 1,000ドル Activity Description ES Duration EF LS Float Costs LEGEND I Setup Scaffold 6 Remove Roof 1,700ドル 5,500ドル Shut Off Electric 4 300ドル Pay Dump Fees 4 600ドル Fill Dumpster 4 1,800ドル New Roofing 8,000ドル Trash to Landfill 3ドル.400 A Add columns "Fixed Cost", "Remaining Cost", and "Actual Cost to schedule B. Add Costs from the AON above to the "Fixed Cost" column C. Set the baseline D. Update the project to 100% complete through 1/20/2025 E. Print out to PDF a "Cash Flow" report with the following items completed: a Name added in the second box on the right b. Update the graph to show "Cost" as bars on primary axis, and "Cumulative Cost" as a line on secondary axis, and days as the primary unit of time. Final Clean 2 1,500ドル
Expert Solution
Check Mark
Knowledge Booster
Background pattern image
Recommended textbooks for you
Text book image
Architectural Drafting and Design (MindTap Course...
Civil Engineering
ISBN:9781285165738
Author:Alan Jefferis, David A. Madsen, David P. Madsen
Publisher:Cengage Learning
Text book image
Residential Construction Academy: House Wiring (M...
Civil Engineering
ISBN:9781285852225
Author:Gregory W Fletcher
Publisher:Cengage Learning
Text book image
Engineering Fundamentals: An Introduction to Engi...
Civil Engineering
ISBN:9781305084766
Author:Saeed Moaveni
Publisher:Cengage Learning
Text book image
Traffic and Highway Engineering
Civil Engineering
ISBN:9781305156241
Author:Garber, Nicholas J.
Publisher:Cengage Learning
Text book image
Fundamentals Of Construction Estimating
Civil Engineering
ISBN:9781337399395
Author:Pratt, David J.
Publisher:Cengage,
Text book image
Construction Materials, Methods and Techniques (M...
Civil Engineering
ISBN:9781305086272
Author:William P. Spence, Eva Kultermann
Publisher:Cengage Learning