Details
Reactor Type |
Pressurized Water Reactor (or PWR) |
Model |
VVER V-320 |
Owner |
Joint Stock Company 'Concern Rosenergoatom' |
Operator |
Joint Stock Company 'Concern Rosenergoatom' |
Timeline
Construction Start |
Friday, 1 August 1986 |
First Criticality |
Tuesday, 8 November 2011 |
First Grid Connection |
Thursday, 24 November 2011 |
Commercial Operation |
Tuesday, 25 December 2012 |
Specifications
Capacity Net |
950 MWe |
Capacity Gross |
1000 MWe |
Thermal Capacity |
3200 MWt |
Design Net Capacity |
950 MWe |
Operational History
Electricity Supplied (GWh)
Energy Availability Factor (%)
Total Electricity Supplied (GWh)
Reactor History
Year |
Reference Unit Power (MWe) |
Annual Time Online (Hours) |
Electricity Supplied (GWh) |
Operation Factor (%) |
Energy Availability Annual (%) |
Energy Availability Cumulative (%) |
Load Factor Annual (%) |
Load Factor Cumulative (%) |
2011 |
950 |
433 |
131.22 |
- |
- |
- |
- |
- |
2012 |
950 |
6858 |
5166.49 |
- |
- |
- |
- |
- |
2013 |
950 |
6662 |
6342.91 |
76.00 |
75.70 |
75.70 |
76.20 |
76.20 |
2014 |
950 |
7691 |
7249.38 |
87.80 |
87.20 |
81.50 |
87.10 |
81.70 |
2015 |
950 |
8346 |
8086.65 |
95.30 |
95.00 |
86.00 |
97.20 |
86.80 |
2016 |
950 |
7255 |
6704.20 |
82.60 |
80.20 |
84.50 |
80.30 |
85.20 |
2017 |
950 |
7490 |
7535.97 |
85.50 |
86.50 |
84.90 |
90.60 |
86.30 |
2018 |
950 |
8760 |
8736.46 |
100.00 |
99.80 |
87.40 |
105.00 |
89.40 |
2019 |
950 |
7745 |
7668.87 |
88.40 |
87.70 |
87.40 |
92.20 |
89.80 |
2020 |
950 |
7638 |
7553.71 |
87.00 |
86.30 |
87.30 |
90.50 |
89.90 |
2021 |
950 |
8657 |
8673.29 |
98.80 |
98.70 |
88.60 |
104.20 |
91.50 |
2022 |
950 |
7987 |
7923.02 |
91.20 |
91.20 |
88.80 |
95.20 |
91.80 |
2023 |
950 |
8100 |
8076.94 |
92.50 |
92.30 |
89.10 |
97.10 |
92.30 |
2024 |
950 |
8764 |
8675.88 |
99.80 |
99.40 |
90.00 |
104.00 |
93.30 |