Procurement Plan for Electric Power Facilities
(Category: Equipment and materials for nuclear power stations)
(All information is subject to change without notice. Please note that our procurement transaction may already be in progress at the time of this announcement.)
NO. Description and Specifications Quantity Unit Required by the below
Expected RFQ
Month
Delivery Month Delivery Terms
1 Vehicle
Inspection of portable diesel injection pumps
Nos. 1 and 2
Disassembly maintenance 1 set Genkai Nuclear Power Station Mar-2025 Jul-2025
Completion of
inspection2Equipment and materials for nuclear power stations (radiation
control equipment/waste control equipment)
Ceramic filter element
Model S6C-26002-D1515A, 184 units; S6C-26002-D1515K,
184 units
1 set Genkai Nuclear Power Station Jun-2025 Jan-2026
Delivery at place
(DAP)3Equipment and materials for nuclear power stations (radiation
control equipment/waste control equipment)
Ceramic filter element
Model S6C-26002-D1515A, 184 units; S6C-26002-D1515K,
184 units
1 set Genkai Nuclear Power Station Jun-2026 Jan-2027
Delivery at place
(DAP)4Equipment and materials for nuclear power stations (radiation
control equipment/waste control equipment)
Ceramic filter element
Model S6C-26002-D1515A, 184 units; S6C-26002-D1515K,
184 units
1 set Genkai Nuclear Power Station Jun-2027 Jan-2028
Delivery at place
(DAP)5Equipment and materials for nuclear power stations (radiation
control equipment/waste control equipment)
Ceramic filter element Model S6C-26002-D1515A; dimensions, ⌀60 ×ばつ 1500 L 168 set Genkai Nuclear Power Station Jun-2025 Jan-2026
Delivery at place
(DAP)6Equipment and materials for nuclear power stations (radiation
control equipment/waste control equipment)
Ceramic filter element Model S6C-26002-D1515A; dimensions, ⌀60 ×ばつ 1500 L 168 set Genkai Nuclear Power Station Jun-2026 Jan-2027
Delivery at place
(DAP)7Equipment and materials for nuclear power stations (radiation
control equipment/waste control equipment)
Ceramic filter element Model S6C-26002-D1515A; dimensions, ⌀60 ×ばつ 1500 L 168 set Genkai Nuclear Power Station Jun-2027 Jan-2028
Delivery at place
(DAP)8Equipment and materials for nuclear power stations (radiation
control equipment/waste control equipment)
Primary/secondary ceramic filter element S6C-26002-D1515K/D1015K, 276 units each 1 set Sendai Nuclear Power Station Apr-2025 Sep-2025
Delivery at place
(DAP)9Equipment and materials for nuclear power stations (radiation
control equipment/waste control equipment)
Primary/secondary ceramic filter element S6C-26002-D1515K/D1015K, 276 units each 1 set Sendai Nuclear Power Station Apr-2026 Sep-2026
Delivery at place
(DAP)10Equipment and materials for nuclear power stations (radiation
control equipment/waste control equipment)
Primary/secondary ceramic filter element S6C-26002-D1515K/D1015K, 276 units each 1 set Sendai Nuclear Power Station May-2027 Oct-2027
Delivery at place
(DAP)11Equipment and materials for nuclear power stations (radiation
control equipment/waste control equipment)
Repair of refractories of miscellaneous
radioactive solid waste incineration facilities
Repair of refractories of miscellaneous radioactive solid
waste incineration facilities
1 set Sendai Nuclear Power Station Jun-2025 Dec-2025
Completion of
repair12Equipment and materials for nuclear power stations (electrical
equipment)
Low-voltage electric motor for the primary
ventilation system
1 set Sendai Nuclear Power Station Jan-2025 Jan-2026
Delivery at place
(DAP)13Equipment and materials for nuclear power stations (electrical
equipment)
Low-voltage electric motor for the primary
system
1 set Sendai Nuclear Power Station Feb-2025 Dec-2025
Delivery at place
(DAP)14Equipment and materials for nuclear power stations (electrical
equipment)
Heat trace equipment cards, etc. 1 set Sendai Nuclear Power Station Feb-2025 Dec-2025
Delivery at place
(DAP)15Equipment and materials for nuclear power stations (electrical
equipment)
Heat trace equipment cards, etc. 1 set Sendai Nuclear Power Station Feb-2025 Dec-2025
Delivery at place
(DAP)16Equipment and materials for nuclear power stations (electrical
equipment)
Secondary-system high-voltage motor stator 1 set Sendai Nuclear Power Station Feb-2025 Feb-2026
Delivery at place
(DAP)17Equipment and materials for nuclear power stations (electrical
equipment)
Reactor control protection system and primary
system transmitter
Transmitter: EJX series 1 set Sendai Nuclear Power Station Jun-2024 Sep-2025 Completion of test18Equipment and materials for nuclear power stations (electrical
equipment)
Reactor control protection system and primary
system transmitter
Transmitter: EJX series 1 set Sendai Nuclear Power Station Sep-2024 Dec-2025 Completion of test19Equipment and materials for nuclear power stations (electrical
equipment)
Measuring instrumentation control system
replacement parts
1 set Sendai Nuclear Power Station Jul-2024 Nov-2024
Delivery at place
(DAP)20Equipment and materials for nuclear power stations (electrical
equipment)
Radiation monitor detector 1 set Sendai Nuclear Power Station Sep-2024 Oct-2025
Delivery at place
(DAP)
Procurement Plan for Electric Power Facilities
(Category: Equipment and materials for nuclear power stations)
(All information is subject to change without notice. Please note that our procurement transaction may already be in progress at the time of this announcement.)
NO. Description and Specifications Quantity Unit Required by the below
Expected RFQ
Month
Delivery Month Delivery Terms21Equipment and materials for nuclear power stations (electrical
equipment)
Radiation monitor detector 1 set Sendai Nuclear Power Station Dec-2024 Jan-2026
Delivery at place
(DAP)22Equipment and materials for nuclear power stations (electrical
equipment)
Excore nuclear instrumentation device
detector
ND-8705 and ND-8709 1 set Sendai Nuclear Power Station Sep-2024 Oct-2025
Delivery at place
(DAP)23Equipment and materials for nuclear power stations (electrical
equipment)
Excore nuclear instrumentation device
detector
ND-8705 and ND-8709 1 set Sendai Nuclear Power Station Dec-2024 Jan-2026
Delivery at place
(DAP)24Equipment and materials for nuclear power stations (primary
system equipment)
Air compressor intercooler for 3B control Horizontal shell and tube type 1 set Genkai Nuclear Power Station Jul-2024 Mar-2025
Delivery at place
(DAP)25Equipment and materials for nuclear power stations (primary
system equipment)
Air compressor intercooler for 4B control Horizontal shell and tube type 1 set Genkai Nuclear Power Station Dec-2024 Jul-2025
Delivery at place
(DAP)26Equipment and materials for nuclear power stations (secondary
system equipment)
Inspection, technical guidance, etc. Inspection, technical guidance, etc. 1 set Sendai Nuclear Power Station May-2025 Dec-2025
Completion of
repair27Equipment and materials for nuclear power stations (secondary
system equipment)
Primary system seawater piping Primary system seawater piping 1 set Genkai Nuclear Power Station Aug-2024 Jun-2025
Completion of testrun28
Equipment and materials for nuclear power stations (secondary
system equipment)
Primary system seawater piping Primary system seawater piping 1 set Genkai Nuclear Power Station Jan-2025 Oct-2025
Completion of testrun29
Equipment and materials for nuclear power stations (secondary
system equipment)
Electrohydraulic governor hydraulic
equipment
Electrohydraulic governor hydraulic equipment 1 set Genkai Nuclear Power Station Nov-2024 Jul-2025
Completion of
inspection30Equipment and materials for nuclear power stations (secondary
system equipment)
Electrohydraulic governor hydraulic
equipment
Electrohydraulic governor hydraulic equipment 1 set Genkai Nuclear Power Station Feb-2025 Nov-2025
Completion of
inspection