Procurement Plan for Electric Power Facilities
(Category: Equipment and materials for thermal and geothermal power stations)
(All information is subject to change without notice. Please note that our procurement transaction may already be in progress at the time of this announcement.)
NO. Description and Specifications Quantity Unit Required by the below
Expected RFQ
Month
Delivery Month Delivery Terms1equipment and materials for thermal power stations
(control facility)
Matsuura unit 1 main control system Matsuura Unit 1 main control system improvement work 1 set Matsuura Thermal Power Station Jun-2024 Jun-2027 Completion of test run2Equipment and materials for thermal power stations
(electrical equipment)
500 kV bushing for Matsuura thermal powerlineProduction, installation and adjustment of bushings for 1 L
and 2 L
1 set Matsuura Thermal Power Station Mar-2025 Oct-2026
Installation, adjustment
and field test3Equipment and materials for thermal power stations
(electrical equipment)
Shin Oita Unit 2 series metal-clad power
center bus protection relay
Renewal of M/C and P/C protection relays 1 set Shin Oita Thermal Power Station Jun-2024 Mar-2025 Completion of test run4Equipment and materials for thermal power stations
(electrical equipment)
Protection relay board for starting
transformer, etc.
Protection relay board for starting transformer, etc. 1 set Reihoku Thermal Power Station Dec-2024 Nov-2026 Completion of test run5Equipment and materials for thermal power stations
(equipment of fuel system)
Matsuura: Shared coal lifting equipment, coal
lifter No. 3, rail clamp repair
Production, replacement, test operation and adjustment of
rail clamps
1 set Matsuura Thermal Power Station Jul-2024 Dec-2025
Installation, adjustment
and field test6Equipment and materials for thermal power stations
(equipment of fuel system)
Matsuura: Shared coal lifting equipment, coal
lifter No. 1
Design, production, new installation, test operation and
adjustment of coal lifters
1 set Matsuura Thermal Power Station Sep-2024 Jun-2026
Installation, adjustment
and field test7Equipment and materials for thermal power stations
(boilers)
2 – 2-shaft HRSG inlet casing repair parts HRSG inlet casing, etc. 1 set Shin Oita Thermal Power Station Jun-2024 Mar-2025 Free on Truck8Equipment and materials for thermal power stations
(boilers)
2 – 3-shaft HRSG inlet casing repair parts HRSG inlet casing, etc. 1 set Shin Oita Thermal Power Station Nov-2024 Apr-2026 Free on Truck9Equipment and materials for thermal power stations
(turbines/generators)
M-BFP fluid coupling actuator, etc. Fluid coupling actuator, positioner, etc. 1 set Shin Kokura Thermal Power Station Apr-2025 Feb-2026 Delivery at place (DAP)10Equipment and materials for thermal power stations
(turbines/generators)
M-BFP water feed control panel unit, etc. Unit in the control panel, etc. 1 set Shin Kokura Thermal Power Station Apr-2025 Feb-2026 Delivery at place (DAP)11Equipment and materials for thermal power stations
(turbines/generators)
2nd turbine oil cylinder Production of oil cylinders for MSV (valves 1, 3 and 4) 1 set Matsuura Thermal Power Station Aug-2024 Aug-2026 Delivery at place (DAP)12Equipment and materials for thermal power stations
(turbines/generators)
Shin Oita Unit 1 – 6-shaft GT fuel valve
disassembly inspection
Fuel valve disassembly inspection ×ばつ 6 units 1 set Shin Oita Thermal Power Station May-2025 Apr-2026 Delivery at place (DAP)13Equipment and materials for thermal power stations
(turbines/generators)
3 – 4-shaft GT air suction filter (EVA cooler
media)
EVA cooler media 1 set Shin Oita Thermal Power Station Nov-2024 Apr-2026 Free on Truck14Equipment and materials for thermal power stations
(turbines/generators)
Gas turbine 1st stage stator blade repair (14
times of output per shaft)
For gas turbine F7FA 1 set Shin Oita Thermal Power Station Nov-2024 Apr-2026 Free on Truck15Equipment and materials for thermal power stations
(turbines/generators)
Gas turbine 2nd stage stator blade repair (14
times of output per shaft)
For gas turbine F7FA 1 set Shin Oita Thermal Power Station Nov-2024 Apr-2026 Free on Truck16Equipment and materials for thermal power stations
(turbines/generators)
Gas turbine F1 cone For gas turbine F7FA 1 set Shin Oita Thermal Power Station Aug-2024 Jul-2025 Free on Truck17Equipment and materials for thermal power stations
(turbines/generators)
Gas turbine premixer For gas turbine F7FA 2 set Shin Oita Thermal Power Station Nov-2024 Apr-2026 Free on Truck18Equipment and materials for thermal power stations
(turbines/generators)
Gas turbine 3rd-stage moving blade For gas turbine F7FA 1 set Shin Oita Thermal Power Station Nov-2024 Apr-2026 Free on Truck19Equipment and materials for thermal power stations
(turbines/generators)
Gas turbine 2nd stage shroud For gas turbine F7FA 2 set Shin Oita Thermal Power Station Nov-2024 Apr-2026 Free on Truck20Equipment and materials for thermal power stations
(turbines/generators)
3 – 2-shaft GT torque converter
Purchase of parts for inspection, and detailed inspection and
transportation of torque converters
1 set Shin Oita Thermal Power Station Aug-2024 Jul-2025 Free on Truck
Procurement Plan for Electric Power Facilities
(Category: Equipment and materials for thermal and geothermal power stations)
(All information is subject to change without notice. Please note that our procurement transaction may already be in progress at the time of this announcement.)
NO. Description and Specifications Quantity Unit Required by the below
Expected RFQ
Month
Delivery Month Delivery Terms21Equipment and materials for thermal power stations
(turbines/generators)
Gas turbine compressor stage 0 moving blade
(for rotor C)
For gas turbine F7FA 1 set Shin Oita Thermal Power Station Jun-2024 Jun-2026 Free on Truck22Equipment and materials for thermal power stations
(turbines/generators)
Gas turbine compressor stage 0 moving blade
(for rotor B)
For gas turbine F7FA 1 set Shin Oita Thermal Power Station Nov-2024 Nov-2026 Free on Truck23Equipment and materials for thermal power stations
(turbines/generators)
3 – 2-shaft ST cabin ST cabin horizontal bolt (high creep bolt) 1 set Shin Oita Thermal Power Station Jul-2024 Mar-2025 Delivery at place (DAP)